Metro's maps now show an underground station at Ventura Boulevard and Van Nuys Boulevard, labeled Ventura/Van Nuys. If you're comparing Sherman Oaks with other Valley neighborhoods this winter, it's tempting to count that station as part of a home's value. The record says to wait. Los Angeles has opened rail lines before. On the last line studied closely, homes near the planned stations sold at a discount during the years of construction, and the premium appeared only after trains started running. Meanwhile, Metro has a more immediate question for Sherman Oaks: where to put the yard that stores and maintains the trains.
What Metro Has Actually Dated
On January 22, 2026, the Metro Board chose what it calls Modified Alternative 5 for the Sepulveda Transit Corridor. It is an underground heavy-rail line, not a monorail, running between Van Nuys Metrolink and the E Line's Expo/Sepulveda station. The trains are automated and run in a single-bore tunnel. The Valley part of the route follows Van Nuys Boulevard and the southern part follows Sepulveda Boulevard, according to Metro's The Source. That choice dropped the elevated structures over Sepulveda Boulevard that were part of an earlier alternative.
Metro plans to build an Initial Operating Segment first. It has four underground stations between the G Line in the Valley and the D Line on the Westside, and Sherman Oaks gets two of them: Ventura/Van Nuys and the G Line connection near Oxnard Street. Every milestone with a published date so far is a planning date.
| Date | What happened |
|---|---|
| January 22, 2026 | Metro Board selects Modified Alternative 5 |
| May 2026 | Metro committee extends environmental and engineering contract work through December 31, 2028 |
| November 2026 | Metro opens scoping for federal review and a recirculated draft environmental report |
| November 23, 2026 | Scoping comment deadline |
Metro's project page says the corridor is in planning and environmental review and that an updated timeline will be shared when it's available. The Sherman Oaks Homeowners Association filed public records requests with Metro, and according to its October 2026 transit update, the records show design work running into March 2027 and environmental work through the end of 2028. Funding is still being assembled too. Measure M sets aside $5.7 billion in 2015 dollars, and Metro says building any version of the line will take more money than that. Metro's preliminary estimate of $24.2 billion was in 2023 dollars and covered the original Alternative 5, not the modified route the board chose.
A buyer can treat the corridor as a firm decision without a firm calendar. A 30-year mortgage written this winter will spend a long stretch of its life before trains reach Ventura Boulevard.
How Nearby Home Prices Moved the Last Time LA Opened a Line
The best local evidence comes from the original Gold Line, which opened in 2003. A study by Noh and Li looked at 89,108 single-family home sales from 1993 to 2013. It split that span into a planning phase from 1993 to 1998, construction and opening from 1999 to 2004, and operation from 2005 to 2013. Before the opening, homes within half a mile of a planned station sold for about 2.88% and 4.14% less than comparable homes in the two periods from 1996 to 2001. The authors read that as single-family buyers avoiding homes near a major road under construction. The discount turned into a premium right after the stations opened, and the half-mile premium kept growing until it reached 7.38% in the final period, eight years after opening.
The gains were not spread evenly. In the study's low-income neighborhoods, the half-mile figure went from minus 6.67% in 1999 through 2001 to plus 10.91% in 2011 through 2013, a larger swing than the study measured across all neighborhoods. For someone buying in Sherman Oaks now, the pattern matters more than any one percentage. The value showed up once riders could use the line. During the years of planning and digging, nearby homes sold at a discount.
Other Los Angeles research is less encouraging. A Lincoln Institute paper by Schuetz and colleagues studied 28 Red, Gold and Purple Line stations that opened between 1992 and 2003. In the five years after each opening, prices per square foot near the stations rose less than in comparable areas farther away. Construction has its own costs. A study in the Journal of Transport and Land Use found that businesses within 400 meters of stations on the Red Line's Vermont/Hollywood segment had 46% greater odds of closing during the 1992 to 1999 cut-and-cover construction. Once the line opened, their odds of closing were lower.
None of this predicts what will happen at Ventura and Van Nuys. It does show that where Los Angeles has paid for rail access, it paid after the trains were running, not when the station was announced.
The Decision That Reaches Sherman Oaks First
The trains need a home base. Metro's November 2026 scoping presentation says the yard sites in the earlier draft fell outside the Initial Operating Segment, so a new maintenance and storage site is needed. It lists five options. Option 1 is the existing Westfield Fashion Square on Riverside Drive, a mall anchored by Bloomingdale's and Macy's. Option 2 is along Oxnard Street between Kester Avenue and Sepulveda Boulevard. Option 3 is Metro's existing parking and nearby properties close to the G Line Van Nuys station. Metro notes that the sites, their sizes and their layouts will be refined as design goes on, and that a combination of sites may be needed.
The homeowners association has taken a position. Its November 2026 transit post asks residents to help stop a maintenance facility in Sherman Oaks and warns that one could mean demolishing Fashion Square or another part of the community. That is the association's concern, not a Metro finding. The same group supported the January route choice over an elevated Valley alignment. It also flagged noise and vibration under residential streets, the number of Valley stations, and cost.
For a buyer, the yard question has a shorter horizon than the station. Metro set November 23 as the deadline for scoping comments, and the yard sites will be studied in the environmental work that follows. Near Fashion Square or the Oxnard Street stretch north of the 101, the open question is one the next round of Metro documents will start to answer. The station benefit for a house a few blocks from Ventura and Van Nuys may be a decade or more away. Pricing the first and ignoring the second is the reasonable order.
What Is Being Built Near the Station Now
Development along Riverside Drive and Van Nuys Boulevard has its own momentum and doesn't depend on a train. Citrus Commons at 14130 Riverside Drive has 249 apartments and 27,000 square feet of retail, including a Trader Joe's, according to Urbanize LA. On the same site, IMT plans to turn the former Sunkist headquarters, a three-story office building of about 125,000 square feet, into 95 homes under the city's adaptive-reuse ordinance, Urbanize LA reported in September. SOHA has questioned how that conversion was approved on its housing page.
Closer to the planned station, an application at 4276 Van Nuys Boulevard proposes replacing a preschool with eight four-story single-family homes, each with room for an ADU. At 14318 W. Dickens Street, a December 2025 application proposed a six-story building with 75 affordable apartments in place of five houses. To the west, Via Avanti at 4815 to 4827 Sepulveda Boulevard is a 325-apartment project with about 40,000 square feet of retail.
These projects will change daily life around Ventura and Van Nuys years before any station opens: more neighbors, more storefronts, more traffic on the streets leading to them. A buyer comparing blocks should weigh them as the actual near-term change. Our guide to Sherman Oaks pockets from Chandler Estates to Library Square covers how differences at the street level already show up in value.
The Valley Market Gives Buyers Time to Check
The current market is slow enough to look into these questions before writing an offer. In October 2026, the San Fernando Valley had 5.3 months of supply across homes and condos, up from 4.4 months in August 2026, according to the Southland Regional Association of Realtors. Homes and condos averaged 48 days on market in October, compared with 39 days in August. October's Valley single-family median was $1,133,000, up 3.0% from October 2025. Closed single-family sales fell 28.3% over the same year, to 390. The October condo median was $595,000, down 4.5% from a year earlier. These are Valley-wide numbers, not Sherman Oaks figures.
With fewer sales and more time on market across the Valley, sellers are less able to collect a premium for a station that's still years away. Buyers can ask a seller how close the house is to the Oxnard Street and Fashion Square yard options, read Metro's scoping map, and price the home on what it is today. Our buyer's guide covers the rest of that preparation. If you're weighing attached homes near the boulevard, see Sherman Oaks condo or townhome.
Questions Buyers Ask About the Line
Which Sherman Oaks stations are in the first phase? Ventura/Van Nuys and the G Line connection near Oxnard Street. Both are among the four underground stations in Metro's Initial Operating Segment, and Metro marks the station locations as subject to change.
Does the line run under Sepulveda Boulevard in Sherman Oaks? In the Valley, the chosen route runs under Van Nuys Boulevard. It follows Sepulveda Boulevard on its southern segment toward the Westside.
Where can I follow the yard decision? Metro's Sepulveda Transit Corridor page posts the environmental documents and meeting materials, and SOHA tracks the project on its transit page.
If you own near Ventura and Van Nuys, Fashion Square, or the Oxnard Street corridor and want to know how buyers are pricing your block while Metro works through its plans, Sean Curts & Associates can walk you through recent nearby sales. Request a free home valuation and we'll show you what the market is paying today.